Equipment Relocation at Major Pharmaceutical Plant
Heritage recently completed the turn-key relocation and re-installation of a 100,000 sqft pharmaceutical plant. The time-sensitive project was performed over 6 weeks, working 12-hour shifts Monday through Saturday from start to completion.
Location:
NJ
Industry:
Pharmaceutical

THE CHALLENGE
Heritage’s scope of work included the following:
- Over 40 trailer loads of manufacturing equipment, vessels, robotic filling lines, shredders, lab equipment, pallet racking, and other associated office infrastructure items were removed and reinstalled at the new location
- Performed all utility disconnects and reconnects, and the final setting and recommissioning of the machinery and equipment
THE EXECUTION
The project was completed safely, on time, and to the client’s satisfaction.